Dual Wall Pipe Installation Guide

Dual Wall Pipe Installation Guide‌

(Complying with ASTM F2648 & EN 13476 Standards)

I. Construction Sequence

  1. Survey & Marking → 2. Mechanical Trenching → 3. Subgrade Compaction → 4. Gravel Base Course → 5. Sand Bedding → 6. Pipe Installation → 7. Manhole Construction → 8. Backfilling → 9. Hydrostatic Test → 10. Final Compaction

II. DWCP Installation Protocol

1. Pre-Construction Preparation

  • Review design drawings to confirm pipeline layout, slopes, and connection requirements
  • Verify existing control points (benchmarks & traverse points) along the alignment
  • Conduct topographic survey, plot as-built sketches, and establish temporary control points

2. Trench Excavation

ParameterRequirement
Trench WidthPipe OD + 0.4–1.0m (min. 600mm working space)
Slope RatioAs per design (typically 1:0.33–1:1 for cohesive soils)
Undisturbed SoilPreserve 200–300mm above design grade; trim manually before pipe laying
Over-ExcavationBackfill with 10–15mm graded gravel or coarse sand (≥95% compaction)
Groundwater ControlInstall sump pumps + 100mm gravel drainage layer where required

3. Pipe Foundation

Soil ConditionFoundation Specification
Stable Soil100mm sand bedding (CBR ≥5%)
Waterlogged Soft Soil150mm crushed stone (5–40mm) + 50mm sand layer (Total ≥200mm)
Organic Soil300mm graded Gobi gravel replacement

4. Pipe Installation

  • Jointing Method‌: Snap-tight couplings with EPDM gaskets (per ASTM D3212)
  • Alignment Tolerance‌: ±10mm vertical/horizontal deviation per 3m length
  • Deflection Limit‌: ≤5% of nominal diameter (post-installation)

5. Quality Control Checks

StageInspection Items
Pre-InstallationPipe certification (ISO 9001), ovality (<3%), rubber ring hardness (50–60 IRHD)
During InstallationBedding compaction, joint seating depth, pipe invert elevation (±15mm)
Post-InstallationHydrostatic test (1.5× working pressure for 30min), deflection measurement

Dual Wall Pipe Installation Guide
Dual Wall Pipe Installation Guide

III. Critical Technical Requirements

1. Backfilling

  • Initial Layer‌: Select backfill to pipe springline (≤300mm lifts, 90% compaction)
  • Final Layer‌: Native soil in 500mm lifts (≥95% compaction for road sections)

2. Manhole Integration

  • Use flexible boot adapters (per ASTM C923) at pipe-manhole connections
  • Apply bentonite waterstop at penetration points

3. Testing Protocols

  • Mandrel Test‌: Pass 95% pipe diameter mandrel through installed pipeline
  • Leakage Test‌: Max 1.25 l/km/day for diameters ≤1000mm (per EN 1610)

‌Ⅳ. Pipe Installation

1. Handling & Placement

MethodSpecification
Manual InstallationLift pipe ends to trench workers (max. 3m depth or ≤DN400 pipes)
Mechanical LoweringUse non-metallic slings for >3m depth/DN400+ pipes (metallic tools prohibited)
Alignment Tolerance±10mm vertical/horizontal deviation per 3m length

2. Jointing Techniques

  • Socket-Spigot Joints‌: Install with spigot facing downstream (per ISO 8639)
  • Spiral Corrugated Joints‌:
    • Methods‌: Electrofusion, extrusion welding, or heat-shrink sleeves
    • Tolerance‌: Max. 2mm radial misalignment

3. Quality Control

  • Cutting‌: Use fine-tooth saws for square cuts (burr-free)
  • Gasket Inspection‌: Verify O-ring position with feeler gauge (0.5-1.0mm gap)
  • Elevation Check‌: Measure crown elevation every 10m (converted to invert)

‌Ⅴ. Manhole Connection

1. Connection Methods

TypeTechnical Requirements
Flexible JointPre-installed EPDM boot adapter (min. 100mm overlap)
Rigid ConnectionM10 cement mortar with 5% calcium sulfoaluminate expansion agent
Precast CollarC15 concrete collar (ID=pipe OD+20mm, thickness≥50mm) + rubber gasket

‌Ⅵ. Backfilling Protocol

1. Compaction Requirements

ZoneCompaction (%)Material
Pipe Foundation85-90Washed sand (0.5-2mm)
Pipe Haunches (2α zone)95Graded gravel (5-40mm)
Pipe Springline to 0.5m90/85*Select backfill (≤10% fines)
Above 0.5m≥80Native soil

*Note: 90% for sides, 85% for top

2. Special Conditions

  • High Water Table‌: Install geotextile (200g/m²) + underdrains
  • Uneven Settlement‌: Use flowable fill (CLSM) for transition zones

‌Ⅶ. Pressure Testing

1. Hydrostatic Test

  • Procedure‌: Fill to 2m head pressure for 24hrs (per GB 50268)
  • Allowable Leakage‌: ≤1.25 L/km/day for DN≤1000mm

2. Alternative Methods

  • Air Test‌: 25kPa for 5min (max. 0.5kPa pressure drop)

‌Ⅷ. Deformation Inspection

1. Post-Installation Check

  • Timeframe‌: Measure within 12-24hrs after final backfill
  • Tolerance‌: Max. 3.3% diameter deflection (2/3 of allowable)

2. Corrective Actions

  1. Expose 85% pipe height (manual excavation within 0.5m)
  2. Replace damaged sections
  3. Recompact with ASTM D698 compliant material
Scroll to Top